The Indian nuclear safety regulator, the Atomic Energy Regulatory Board (AERB), has granted permission for the first approach to criticality for the eighth unit of the Rajasthan Atomic Power Plant (RAPP-8), located in Rawatbhata, Chittorgarh. This marks a significant achievement in India's domestic nuclear sector.
The AERB approval, received on November 19, signifies a substantial step towards bringing the patented 700 MW heavy water reactor closer to commercial power generation, provided that prescribed tests are successfully completed and regulatory clearances are obtained. The First Approach to Criticality (FAC) is the stage where a nuclear reactor begins a controlled, self-sustaining chain nuclear reaction at low power. Fuel loading into the 700 MW-8 unit began in September.
The AERB clearance was issued following a comprehensive analysis of the reactor design, construction progress, commissioning tests, and operational readiness. This regulatory process involved detailed assessments by AERB and its safety committees, as well as regulatory inspections and discussions at the AERB Council meeting, according to the government on Friday.
RAPP-8 is the fourth unit of the 700 MW PHWR series developed and built in India. The other three units of this design are located at the Kakrapar Atomic Power Station in Gujarat, along with RAPP-7 in Rajasthan. There are currently eight nuclear power plants operating at this site.
India's PHWR series forms the basis of the first phase of the country's three-stage nuclear energy program. These reactors use heavy water as a moderator and coolant, and natural uranium oxide as fuel. The series, designed by the Bhabha Atomic Research Centre (BARC) and operated by the Nuclear Power Corporation of India Limited (NPCIL), has been scaled from 220 MW to 540 MW and 700 MW units.
Currently, 19 units of various types operate in India (14 IPHWR-220, 2 IPHWR-540, and 3 IPHWR-700), and another 13 IPHWR-700 reactors are planned or under construction. India currently has an installed nuclear capacity of 8.78 GW across 24 operational reactors, providing approximately 3.1% of the total electricity generation in 2025–26. As part of the Nuclear Energy Mission, the country plans to reach a target of 100 GW by 2047. Nine reactor units are currently under construction (total capacity 7.5 GW), including a 500 MW Prototype Fast Breeder Reactor (PFBR) which achieved first criticality in April of this year; ten additional reactors are in the pipeline.