Nuclear Safety Regulator AERB Approves First Approach to Criticality for N-plant Unit-8 in Rajasthan
Read more
The times of India
timesofindia.indiatimes.com

Nuclear Safety Regulator AERB Approves First Approach to Criticality for N-plant Unit-8 in Rajasthan

The Indian nuclear safety regulator, the Atomic Energy Regulatory Board (AERB), has granted permission for the first approach to criticality for the eighth unit of the Rajasthan Atomic Power Plant (RAPP-8), located in Rawatbhata, Chittorgarh. This marks a significant achievement in India's domestic nuclear sector.

The AERB approval, received on November 19, signifies a substantial step towards bringing the patented 700 MW heavy water reactor closer to commercial power generation, provided that prescribed tests are successfully completed and regulatory clearances are obtained. The First Approach to Criticality (FAC) is the stage where a nuclear reactor begins a controlled, self-sustaining chain nuclear reaction at low power. Fuel loading into the 700 MW-8 unit began in September.

The AERB clearance was issued following a comprehensive analysis of the reactor design, construction progress, commissioning tests, and operational readiness. This regulatory process involved detailed assessments by AERB and its safety committees, as well as regulatory inspections and discussions at the AERB Council meeting, according to the government on Friday.

RAPP-8 is the fourth unit of the 700 MW PHWR series developed and built in India. The other three units of this design are located at the Kakrapar Atomic Power Station in Gujarat, along with RAPP-7 in Rajasthan. There are currently eight nuclear power plants operating at this site.

India's PHWR series forms the basis of the first phase of the country's three-stage nuclear energy program. These reactors use heavy water as a moderator and coolant, and natural uranium oxide as fuel. The series, designed by the Bhabha Atomic Research Centre (BARC) and operated by the Nuclear Power Corporation of India Limited (NPCIL), has been scaled from 220 MW to 540 MW and 700 MW units.

Currently, 19 units of various types operate in India (14 IPHWR-220, 2 IPHWR-540, and 3 IPHWR-700), and another 13 IPHWR-700 reactors are planned or under construction. India currently has an installed nuclear capacity of 8.78 GW across 24 operational reactors, providing approximately 3.1% of the total electricity generation in 2025–26. As part of the Nuclear Energy Mission, the country plans to reach a target of 100 GW by 2047. Nine reactor units are currently under construction (total capacity 7.5 GW), including a 500 MW Prototype Fast Breeder Reactor (PFBR) which achieved first criticality in April of this year; ten additional reactors are in the pipeline.

Similar stories

Northeast Railway Completes Electrification of All Operational Sections
Read more
www.aajtak.in

Northeast Railway Completes Electrification of All Operational Sections

A significant goal has been achieved for the railway network of northeastern India: all operational railway sections under the jurisdiction of the Northeast Frontier Railway (NFR) have been fully electrified. As a result, the electrification of railway lines in the northeastern states reached a total volume of 4311.96 route kilometers. Notably, this work was completed in less than a decade.

This achievement is expected to lead to increased efficiency and reliability of train movement in the region. Kapinjal Kishore Sharma, the main public relations representative of NFR, announced this on Tuesday in Guwahati. He specified that before 2014, railway electrification in the northeastern region had not taken place. Work on railway modernization and the promotion of environmentally friendly transport began in 2017–2018.

According to NFR data, a total of 4311.96 route kilometers of railway lines were electrified by 2026–27, with Assam leading this process. The pace of electrification has significantly accelerated in recent years. In 2023–24, 915.62 route kilometers were electrified, and in 2024–25, 1141.38 route kilometers. Furthermore, 445.66 route kilometers were completed in 2025–26, and another 141.77 route kilometers were accomplished by 2026–27.

The electrification of two important railway sections was recently completed: the Lumding-Badarpur section in Assam was finished on September 14, 2026, and the Bairabi-Sairang railway section in Mizoram received electrification on October 12, 2026.

Electrification is also being carried out in parallel with new NFR railway line projects. The aim is to equip new lines with electric traction systems even before their operation begins. The railway company notes that using electric trains will reduce dependence on traditional fuel, help save energy, improve operations, and decrease negative environmental impact. This achievement is also an important step towards the Indian Railways' goal of fully electrifying the mainline network.

Popular