The Supreme Court (SC) has issued a decision that provides significant relief to hundreds of thousands of homebuyers. The Court ruled that in cases where housing projects remain incomplete, even if banks have paid substantial portions of loan installments to unscrupulous or insolvent developers, commercial courts, NCLT, or NCLAT do not have the authority to demand reimbursement from apartment buyers to financiers before investigating any 'improper' connection between the banks and the developers.
This ruling was delivered by a bench comprising Chief Justice Surya Kant, along with Justices Joymalya Bagchi and Vin Mohan. It was made at the request of homebuyers in the Krishna Housing project in Gurgaon, which was being developed by Raheja Developers and subsequently entered insolvency proceedings.
The plaintiffs alleged that a bank had initiated legal action to recover funds against them in a commercial court in Saket, New Delhi, despite them not yet having received their apartments. The bench, led by the Chief Justice, stated that the commercial court's duty is to establish the relationship between the developer and the bank's employees, as well as to verify whether the loan was disbursed strictly in accordance with the tripartite agreement.
The Court emphasized that unless a definitive conclusion is reached that the homebuyers are in default of obligations, no interim orders regarding installment payments can be issued. The civil court was directed not to take any coercive action against the plaintiffs or similarly situated persons until the aforementioned issue is clarified.
According to the tripartite agreement among the buyers, the developer, and the banks, the financier was supposed to transfer the loan amount directly to the developer proportionate to the construction progress on the site. However, in many instances, due to connections between the developer's staff and the banks, financial institutions disbursed loan amounts to each buyer significantly higher than what should have been allocated to the developer, considering the stage of the housing project's construction.
When a project remained unfinished for decades, the bank filed recovery suits against homebuyers who continued to pay monthly installments (EMI) and rent without receiving their apartments. Issuing a judgment in such a suit would impose a heavy financial burden on the homebuyers.
Last September, the bench, under Justice Kant, ordered a CBI investigation into numerous developers and banks across India for collusion aimed at the improper use of the tripartite subsidy scheme and defrauding homebuyers, even when projects remained incomplete for decades.
The bench noted that its sympathy for homebuyers had effectively opened the floodgates for litigation, leading thousands of victims of developer and bank tyranny to approach the Supreme Court directly. The Court stated that 'our hands are overloaded, and we may not be able to handle a new lawsuit.'
In a similar case from Bengaluru involving over 4,000 homebuyers, the court protected the buyers from potential lawsuits by banks because the housing project had remained incomplete for nearly ten years, despite the plaintiffs having paid 95% of the apartment's cost. After providing protection, the bench advised the plaintiff's lawyer to seek appropriate assistance from the High Court of Karnataka.