Uzbekistan commissioned the new 500 kV Khalk substation with a total capacity of 1.602 MVA on November 7.
This facility is designed to increase the reliability of electricity supply to Tashkent and surrounding areas while reducing the load on existing power grids. This substation is one of the largest high-voltage infrastructure projects in the country, and its commissioning will allow for the redistribution of electrical loads between the capital and neighboring districts.
It is expected that the reduction in load on the Tashkent Thermal Power Plant will enable the cessation of using mazut as fuel. Thus, the project aims not only to strengthen energy supply stability but also to improve the environmental situation by reducing emissions of pollutants into the atmosphere.
The total cost of the project, in which the World Bank participated, amounted to 171.4 million US dollars. In addition to the Khalk substation itself, the project included the construction of 213 km of 220 kV overhead power lines and 72 km of 500 kV lines. The total length of the new high-voltage lines is 285 km.
The new infrastructure will expand the capabilities for electricity transmission in Uzbekistan's unified power system, ensure more efficient distribution of electric flows, and help meet the growing demand for electricity. Final work is currently underway to fully integrate the new facilities into the national power system.