Large wind power plants contributed to a sharp increase in private capacity registrations
Read more
TechCentral
techcentral.co.za

Large wind power plants contributed to a sharp increase in private capacity registrations

The energy regulator Nersa registered 3.13 GW of new generating capacity between July and September. This figure is almost four times higher than the 804 MW registered in the previous quarter, thanks to an increase in the number of large wind farms and solar installations.

According to a statement by Nersa published on Thursday, 144 registered facilities this quarter have an estimated investment value of 78.2 billion Rands. This amount approaches the 85 billion Rands registered throughout 2023 and exceeds the figures of any previous full calendar year.

Previously, over five quarters, the registered capacity never exceeded 2 GW, and the investment value peaked at 51.9 billion Rands.

Smaller, but larger projects

Three wind facilities—two located in the Western Cape and one in Mpumalanga—provide 1.06 GW, accounting for about a third of the quarterly capacity. Solar photovoltaic (PV) installations accounted for 139 facilities and 2.05 GW. The remaining capacity is provided by one 3 MW energy storage system and a 18 MW cogeneration plant that produces both heat and electricity, all located in KwaZulu-Natal.

The ability to register such large wind farms became available due to reforms implemented during power outages. In 2021, the government increased the limit on generation projects exempt from licensing from 1 MW to 100 MW, and then completely abolished this limit in December 2022. Since then, projects of any size can be registered with Nersa instead of applying for a generation license.

The shift towards larger projects is evident when compared to the same quarter last year, when Nersa registered 181 facilities with a total capacity of 1.4 GW and investments of 30.8 billion Rands. In the current period, 37 fewer facilities were registered, but the capacity more than doubled, and the average facility capacity grew from 7.7 MW to 21.7 MW.

Almost all the new capacity will be connected to the Eskom grid: 76 facilities totaling 3.08 GW and 77.6 billion Rands. The remaining 68 facilities will connect to municipal grids and provide only 50 MW.

Gauteng registered the highest number of facilities with 47, but their total capacity is only 25 MW, with each facility having a capacity of about half a megawatt. The Western Cape led in capacity and investment, showing 36 facilities, 1.19 GW, and 24.6 billion Rands. Free State (543 MW) and Limpopo (484 MW) followed in terms of capacity.

Faster, but not the fastest

Nersa reported processing applications in an average of nine working days, which is a 'notable improvement' compared to the 10 days required in the same quarter last year. In April-June, processing times were also 10 days, whereas in January-March, Nersa recorded an average time of eight days.

Registered, but not built

Since the start of the registration regime in 2018, Nersa has registered 2,763 facilities with a cumulative capacity of 23.26 GW and an estimated investment value of 487.7 billion Rands. For the remaining quarter of 2026, the annual total is 380 facilities, 5.26 GW, and 126.6 billion Rands, contrasting with the figures of 7.46 GW and 158 billion Rands for the entire year 2025.

It is important to note that registration is a regulatory step, and Nersa's statement does not specify how many of these projects have reached the construction or commercial operation stage.

The new 2.05 GW of solar capacity also feeds into the grid, which is already struggling to absorb daytime generation, posing a hidden risk for private use deals. As stated by Gavin Hurford, Acting CEO of the system operator at the South African National Power Utility, in October: 'We had a particularly difficult time in the winter of 2026, when we observed generation curtailment down to 3000 MW on a certain day.'

Similar stories

Uzbekistan explains discrepancy in electricity generation data
Read more
uzdaily.uz

Uzbekistan explains discrepancy in electricity generation data

The Ministry of Energy of Uzbekistan reported that the discrepancy between the data presented by the Ministry of Energy and the Statistical Committee is due to the fact that official statistical reports do not account for electricity generated by small solar panels installed on building roofs.

According to the ministry's data, Uzbekistan generated 69.6 billion kWh of electricity over the nine-month period (January–September 2026). Thermal power plants provided generation at a level of 49.1 billion kWh.

Additional capacity was generated by large-scale solar and wind power plants, which produced 10.5 billion kWh, while hydroelectric power plants contributed 6.6 billion kWh. Additionally, 2.5 billion kWh was obtained from small rooftop solar installations.

During the same period, block stations generated 867.1 million kWh. The ministry clarified that it was precisely the electricity produced by small solar installations that caused the differences in figures provided by the two agencies.

It is emphasized that electricity generated by solar panels installed by households and legal entities is not included in the summary data compiled by the Statistical Committee. Consequently, when comparing information from the Ministry of Energy and the Statistical Committee, differences in the methodology for accounting for small solar installations must be taken into account.

Eurasian Development Bank: Uzbekistan's Renewable Energy Growth Outpaces Grid Capacity
Read more
uzdaily.uz

Eurasian Development Bank: Uzbekistan's Renewable Energy Growth Outpaces Grid Capacity

According to the Eurasian Development Bank (EDB) report, Uzbekistan has become a key hub for demand, generation, transit, and integration of renewable energy sources within the interconnected energy system of Central Asia. However, the rapid growth in solar and wind generation capacity exceeds the grid's ability to absorb new output.

In its study, 'Energy Without Borders: The Architecture of Energy Connectivity in Central Asia,' the bank points to serious issues in Uzbekistan's power sector, including winter gas shortages, overloaded transmission lines, and a growing reduction in renewable energy generation.

Key Indicators of the Energy Sector

Uzbekistan supplies 23.1 GW out of the total installed capacity of 38.5 GW in the interconnected Central Asian system, making it the largest generating country in this regional union. As of January 1, 2025, Uzbekistan's installed capacity consisted of 17.5 GW of thermal generation, 2.25 GW of hydropower, 0.9 GW of wind, and 2.4 GW of solar.

Other participants in the system have significantly smaller generation capacities: Tajikistan has 6.5 GW, Southern Kazakhstan has 4.77 GW, and Kyrgyzstan has 4.13 GW. Uzbekistan's main energy resources are thermal generation, which includes gas turbine units, gas turbines, and gas engine sets, as well as RES facilities and Battery Energy Storage Systems (BESS).

Generation and Consumption Challenges

EDB Senior Analyst Demir Kabylbayev noted that Uzbekistan is a major demand center and currently a center for RES implementation. Despite significant installed capacity, Uzbekistan faces limitations in electricity production during autumn and winter due to natural gas shortages and internal transmission bottlenecks.

The report estimates the gas-related generation deficit to be between 100–400 MW. Kabylbayev explained that winter demand for natural gas is rising across all consumer groups, leading to insufficient fuel at power plants when electricity demand sharply increases. Consequently, generation capacity is limited by the available gas pressure in pipelines.

During the peak annual load in 2024, the interconnected Central Asian system had an installed capacity of 36.4 GW, but only 28.8 GW was available for generation. Fuel-related constraints across the region reduced the available capacity by 1,081 MW. Kabylbayev warned that building additional power plants may not solve the deficit problem if the new facilities are located outside overloaded transmission points or do not receive sufficient gas during peak hours.

RES Challenges

The expansion of renewable energy presents another challenge. According to Uzbekistan's strategic plans, RES capacity could reach 25 GW by 2030. Of the 62.8 GW of new generation capacity announced by Central Asian countries by 2035, Uzbekistan is responsible for 25 GW. Conservative forecasts suggest that by 2028, Uzbekistan's RES capacity will reach 11.4 GW, and energy storage capacity will be 4.3 GW.

However, this expansion is expected to increase the volume of renewable electricity that the system cannot absorb. According to calculations by the Energy Coordination and Dispatch Center, in 2026, Uzbekistan will need to use 13.1 billion kWh of renewable energy, with a reduction of 2.1 billion kWh. In 2027, usage is projected at 18.5 billion kWh, with a reduction of 2.9 billion kWh. By 2028, these figures are expected to rise to 22.1 billion kWh and 3.5 billion kWh, respectively. The reduction is predicted to be particularly significant during transitional months, potentially reaching 45.7% in September and 37.5% in May.

Kabylbayev noted that the calculations were made in 2024, whereas Uzbekistan has since increased RES generation faster than expected, likely leading to exceeding initial targets. One fundamental challenge is the variability of solar and wind generation, which cannot be controlled like traditional power plants. Kabylbayev explained: 'We do not know when the sun or the wind will be there.'

Regional Coordination and Infrastructure

The EDB report warns that the curtailment of RES generation reduces the actually utilized amount of electricity, worsens project economics, and increases requirements for reserve generation capacity. Payment obligations under long-term power purchase agreements may remain in force even with reduced generation, potentially shifting additional costs onto electricity buyers, system operators, or consumers.

The bank identifies regional coordination as a potential way to mitigate these risks. Stronger cross-border connections, access to flexible hydropower, energy storage, and more accurate market price signals could allow surplus renewable electricity to be absorbed into a wider regional market.

Transmission line overload is already affecting several critical parts of Uzbekistan's network. Flows between Uzbekistan and Kyrgyzstan through the Fergana energy hub reached 2,940 MW against allowable levels of 1,800 MW or 2,600 MW, representing 113% of the applicable limit. The internal segment of the Sagniana–Guzar–Talimarjan transmission line operated at 105% of its permitted capacity, transmitting 1,570 MW against a limit of 1,500 MW.

Network overload also limits Uzbekistan's ability to import hydropower from neighboring countries. According to Kabylbayev, Tajikistan has already become a balancing resource for Uzbekistan's solar generation, with summer electricity imports exceeding winter imports two to three times. Nevertheless, constraints on 220 kV networks prevent some of this electricity from reaching its intended destination. Kabylbayev mentioned the Fergana hub in Surkhandarya, where overload required redirecting approximately 40% of planned summer hydropower imports from Tajikistan to other regions of Tajikistan.

Integration Improvement Proposals

To improve RES integration, the EDB proposes combining battery energy storage systems for fast balancing, conventional hydropower for operational regulation and seasonal flexibility, and pumped-storage hydroelectric power plants for transferring surplus daytime renewable electricity to periods of high demand. Estimates suggest that Uzbekistan's pumped-storage potential is 5,030 MW across 16 facilities in seven regions. The Tashkent region accounts for 46% of this potential, equivalent to 2.3 GW.

Among the proposed projects are the Verkhniy Pskem pumped-storage plant with a capacity of 600 MW, estimated at $1.02 billion, and the Khojikent project with a capacity of 200 MW, estimated at $320 million. The Karateren project will provide 500 MW at a cost of $477 million, and the Aidarkul project will have a capacity of 300 MW at a cost of $350 million. Together, these four projects represent a planned capacity of 1,600 MW and estimated investments of $2.167 billion, with a potential annual output of up to 2.8 billion kWh. The report cautions that the value of these projects must be confirmed by detailed power system operation calculations.

Kabylbayev explained that pumped-storage plants use surplus electricity to pump water to a higher elevation, allowing it to be released for power generation when needed. He stated: 'These 5 GW will work more efficiently if we have regional coordination.'

Priority Infrastructure Projects

EDB also highlighted several priority transport infrastructure projects directly affecting Uzbekistan. The first group of priorities, expected to yield relatively quick benefits and linked to the World Bank's REMIT program, includes the reconstruction of the Kristall–Yulduz connection with a second 220 kV loop between Uzbekistan and Kyrgyzstan via the Fergana hub. This also includes the second 500 kV transmission line between Shymkent and the Tashkent Thermal Power Plant, connecting Uzbekistan and Kazakhstan. An alternative route between Shymkent and the Khalka substation is being considered.

Second priority projects include the Datka–Sugd transit connection with connection to the Lochin substations, the Syrdarya/ACWA–Sugd project, financed by the Asian Development Bank, and the Muruntau–Shymkent connection. The Muruntau–Shymkent project was proposed by the National Dispatch Center and the National Electric Grids of Uzbekistan to reduce overloading in the southwestern transmission sectors.

Third strategic options include the Atamirat–Guzar and Dashoguz–Muruntau–Kyzylorda connections, designed to facilitate the transfer of generating capacity from Turkmenistan. EDB estimates that broader integration of Central Asian energy systems could generate gross regional income of up to $640 million annually. Net benefits from partial and deeper integration are estimated at approximately $120 million. The authors emphasize that the benefits of regional integration will not be distributed evenly among participating countries.

Popular