Redefine Properties has launched a 106 million Rand solar power plant on the roof of a warehouse in Brackengate, Cape Town. This installation will transmit electricity through the city grid to three of the company's properties. The project was realized three years after its initial announcement and exceeded the original budget by 20 million Rands.
Last week, the property group commissioned this 7 MWp station at the Massmart distribution center. It is expected to generate 9.89 GWh annually, which will be fed through the Cape Town network to Kenilworth Centre, Blue Route Mall, and The Towers office complex under a 20-year agreement.
For comparison, according to Engineering News, the city-wide energy transmission program moved about 3.1 GWh between private generators and consumers by September. However, the Redefine station alone will produce more than three times that amount per year, even though the overall program only started this year.
When Redefine first announced the project in September 2023, it described a 5.5 MWp system that was supposed to generate 8.8 GWh annually with an estimated cost of 86 million Rands, as reported by Green Building Africa. Implementation was planned to take about 60 weeks and occur during 2024.
By August 2024, the structure had been increased to 6.2 MW, and the connection had to be postponed to another municipal substation due to design principles not meeting city requirements and standards for installations over 5 MW, according to Engineering News. Johan Nell, Head of Development and Industrial Asset Management at Redefine, informed the group's capital markets day that the commissioning had been moved to the fourth quarter of 2025.
The completed power plant is equipped with 11,691 panels, placed on a roof area of approximately 57,000 m². It connects to the municipal grid via the Rubicon substation using a dedicated mini-substation, inverter station, and transformer yard, utilizing about 300 km of cable.
Pool Filling
The project cost increased by approximately 23%, but the capacity increased by approximately 28%, so the cost per peak watt hardly changed: about 15.60 Rands in 2023 versus about 15.10 Rands now, according to TechCentral calculations. Leon Kok, Redefine's Chief Operating Officer, noted that 'the project goes far beyond a standard rooftop solar panel installation. It reflects the level of engineering and coordination required to ensure viable large-scale energy transmission.'
Energy transmission in Cape Town began in September 2023 when Growthpoint Properties and trader Etana Energy transmitted solar energy from Growthpoint's Constantia Village shopping center to an office building on Foreshore. In April of this year, the first total distribution volume in the city, including these two companies, supplied energy from the Free State hydroelectric power station to five Growthpoint buildings.
The pool system allows the city to distribute energy among multiple properties instead of matching one generator with one consumer, which benefits a landlord with many properties. In Brackengate, a large industrial roof generates energy used by shopping centers and offices. Kok emphasized: 'By using the capacity of one asset to support others, we create a more efficient and sustainable portfolio.'
In September, city energy committee member Xanthea Limberg stated that the city intends to open energy transmission to the market 'in the coming months, if all goes according to plan,' adding that 'consumers using the transmission continue to pay corresponding network and subsidiary charges.'
Redefine has not disclosed what share of the energy needs of the three properties this station will cover or what economic benefits it expects. In 2024, the company reported that Brackengate compensates for over 25% of the total energy consumption of Kenilworth Centre and Blue Route Mall. Since then, The Towers has been added to the scheme.